         Observing Program
        
         
          CONT08
         
        
 
         Continuous VLBI Campaign 2008
        
 
 
         This web page will undergo frequent updates as the planning of the CONT08 campaign progresses.
          Please send a message to the
         
          Coordinating Center
         
         if you have updates or links to be included on this page.
         
         CONT08 is a two-week campaign of continuous VLBI sessions, scheduled for observing during the
          second half of August 2008. The CONT08 campaign will continue the series of the very successful
          continuous VLBI campaigns that were observed at irregular intervals: CONT94 (January 1994),
          CONT95 (August 1995), CONT96 (fall 1996), CONT02 (October 2002), and CONT05 (September 2005).
         
         The plan for the CONT08 campaign is to acquire state of the art VLBI data over a two-week period
           to demonstrate the highest accuracy of which VLBI is capable. Further, it shall support high
           resolution Earth rotation studies. As the diurnal and sub-diurnal signals in the atmospheric
           excitation functions are large in the northern hemisphere summer months, an observation period
           during the summer is preferable. A number of scientific and technical goals are set for the
           campaign:
          
          
           
            Science:
           
           Analysis of the two weeks of continuous high frequency (sub-daily)
             Earth Orientation Parameters (EOP) will address the discrepancies seen between the theoretical
             models (ocean tidal and atmospheric) and the observations at the M2 and S1 frequencies as well
             as between long-term and short-term values of tidal amplitudes. The previous CONT campaigns
             allowed already to study high frequency EOP variations to some extend. With the planned 512
             Mb/s recording and a network with larger geographical coverage the sub-daily precision is
             expected to be better than earlier CONT campaigns, thus clarifying even more the deviations
             from the ocean tide model and allowing for testing further theoretical models. First detection
             of ter-diurnal signals related to M3 and S3 tidal phenomena in the oceans and the atmosphere
             was achieved with the CONT94, CONT02, and CONT05 data. The anticipated precision of the CONT08
             will allow investigating these phenomena in much more detail.
           Previous CONT campaigns were also successfully used to monitor ionospheric activity with
             geodetic VLBI and in particular to derive maps of total electron content (TEC). The planned
             CONT08 network will have a larger geographical coverage than pervious CONT campaigns, and
             thus promises to be more sensitive to smaller scale features in the ionospheric activity.
             Also a combination with complementary techniques like GPS for the derivation of TEC maps will
             be possible.
           
            Technique improvement:
           
           Continuous VLBI data allows comparison of estimates
             of troposphere zenith delay and gradients across experiment boundaries as a measure of the
             accuracy of the observations and analysis. Comparison with WVR measurements where possible
             will be especially useful. Experience from previous CONT campaigns shows the importance of
             observing tropospheric parameters with several complementary instruments for the derivation
             of robust geodetic results in particular for reference frame investigations.
           Besides comparisons to WVR results, comparisons with GPS estimates and with Numerical Weather
             Models (NWM) will be of great importance. First investigations to use high resolution numerical
             weather models to derive mapping functions were tested with previous CONT data. This approach
             proved to be successful and should be continued more intensively with CONT08 and combined with
             modeling of atmospheric turbulence. Also the application of NWM derived tropospheric gradients
             for the geodetic VLBI analysis shall be further tested.
           
            Accuracy assessment:
           
           Analysis of reference frame repeatability day to day can be made
			 and compared with previous continuous VLBI series. In particular the rigorous combination of
             reference frame realizations can be investigated. Continuous VLBI sessions have proved to be
             a very important source of information for these investigations.
          
           
            Comparisons:
           
           All stations have
           
            IGS
           
           GPS systems relatively nearby
			 that are considered Global Stations, three stations are co-located with an
           
            ILRS
           
           SLR system, and four stations are co-located with an
           
            IDS
           
           DORIS station.
			 The continuous high accuracy allows investigation of daily and sub-daily site motions for comparison
			 with external factors such as atmospheric effects and temperature distortions of the antennas or
			 pedestals.
           
         The 15 days of continuous VLBI observation have been fixed as follows:
          
          
           first observation: Tuesday August 12, 2008 @ 00:00:00 UT
          
           last observation: Tuesday August 26, 2008 @ 23:59:59 UT
           
         The following network resources will be used during the CONT08 campaign:
          
          
           Observation network: 11 stations alloted observing time for the 15 session days of
			     the CONT08 campaign. The stations are:
           
 
 
            
             
              | Name | Code | Observatory name and location |  
              | HARTRAO | Hh | Hartebeesthoek Radio Astronomy Observatory, South Africa |  
              | KOKEE | Kk | Kokee Park Geophysical Observatory, Kauai, HI, USA |  
              | MEDICINA | Mc | Medicina Radio Astronomy Station, Italy |  
              | NYALES20 | Ny | Ny Ålesund Geodetic Observatory, Spitsbergen, Norway |  
              | ONSALA60 | On | Onsala Space Observatory, Sweden |  
              | SVETLOE | Sv | Svetloe Radio Astronomy Observatory, Russia |  
              | TIGOCONC | Tc | Transportable Integrated Geodetic Observatory (TIGO), Concepción, Chile |  
              | TSUKUB32 | Ts | Tsukuba VLBI Station, Japan |  
              | WESTFORD | Wf | Westford Antenna, Haystack Observatory, MA, USA |  
              | WETTZELL | Wz | Fundamentalstation Wettzell, Germany |  
              | ZELENCHK | Zc | Radioastronomical Observatory Zelenchukskaya, Russia |  The geographical distribution of these stations is depicted in the
				network map.
 
 
   
 
           The CONT08 stations committed to a pre-campaign station checkout to ensure that the data
                   acquired during the campaign are of the highest quality. Instructions and advice about what
                   to check and how are handled by the Network Coordinator.
          
           Rapid disk return for the "R" type sessions during the CONT period so that IVS can keep up its
                   commitment for two rapid-turnaround sessions each week.
           
         In order to make sure the stations are in good operating condition before CONT08, a set of tests
           is being developed under the direction of
         
          Brian Corey
         
         and
         
          Ed Himwich
         
         for each station to perform. These
           tests will be based on the similar tests that were done for previous CONT experiments, the last of
           which was three years ago.
         
         The schedule will be a standard geodetic schedule which achieves simulated EOP results of at least
           as good as 35 micro-arcsec for pole position and 1.3 micro-sec for UT1. The recording mode will be
           the Mark 5 non-fanout mode with 512 Mb/s data rate.
         
         The
         
          media usage plan and shipment schedule
         
         as of July 7, 2008 is posted.
           The information will be updated when new information comes in.
         
         The detailed observing schedules for CONT08 will be generated using the automatic scheduling algorithms
           of the NASA sked program. We will investigate the best combination of scheduling parameters, minimum SNR
           levels, source list, and flux models. The "best" schedule will be determined as a compromise between the
           optimum simulated formal errors, number of observations, number of scans per hour, sky coverage, and
           robustness.
         
         The schedule and corresponding notes files are available from the Data Centers. Each CONT08 day has
           its own schedule. A detailed description of the observing schedule is available in the
         
          CONT08 session notes
         
         .
         
         From the log files submitted by the stations performance plots have
           been created (PostScript format). Please follow the link to the respective
           station.
         
         
          
           | Station | Plots for all days |  
           | Hartebeesthoek | Hh |  
           | Kokee Park | Kk |  
           | Medicina | Mc |  
           | Ny Ålesund | Ny |  
           | Onsala | On |  
           | Svetloe | Sv |  
           | TIGO | Tc |  
           | Tsukuba | Ts |  
           | Westford | Wf |  
           | Wettzell | Wz |  
           | Zelenchukskaya | Zc |  
 |